27 May 2019   

2min read
It’s been a busy couple of months at Sway with Stage 2 really taking shape. Take a look at our latest drone footage to see the progress!

Here's our construction update for Sway:

  • Slabs have been poured on over 80% of homes
  • Stage 1: Coby townhomes now have third storey framing completed (wow, what a view!)
  • Stage 1: Asha and Audrey townhomes have external painting almost complete and internal sheeting and tiling well underway
  • Stage 1: Evelyn and Byron townhomes have commenced internal sheeting
  • Stage 2: townhomes facing Birtinya Boulevard are racing ahead with rooves already on and internal sheeting commenced
  • Stage 2: Dora townhomes now have frames up
  • Pool excavation is due to start this week!



}