27 December 2018 3 min read

We wanted to share some exciting updates on the amenities we are delivering in the community.
• The Bokarina Boulevard and Nicklin Way intersection has been completed. You can now drive through a number of streets in the south of the site to see the community first-hand!
• The lake has been constructed with landscaping and park to be completed around March - April 2019.
• The new pedestrian underpass and waterway connection will be open to the public for access in March - April 2019.
• Construction of the new beach access will commence between January - February 2019.
• The new village park will commence construction between March - April 2019.

}