08 April 2020 2 min read

Welcome to another construction update for Newport Townhomes. We are very excited about the progress of our new Townhomes and want to share the latest details with you!

Check out the drone video to see our latest progress >> WATCH VIDEO

 

LAKEVIEW RELEASE
Our Newport Townhomes opposite Spinnaker Park and Newport Lake are progressing well and due for a June 2020 completion.

 Lots 3801 to 3806

  • 100% fully waterproof (all windows and doors)
  • tiling underway
  • kitchens 75% installed
  • internal paint ongoing
  • internal joinery and fitout carpentry at 60%
  • driveways and footpaths at 70%
  • landscape works have commenced

 

 

CENTRAL RELEASE
The Newport Townhomes Central Release is slightly behind the Lakeview Release due to weather and is tracking for a July/August 2020 completion.

Lots 1332 to 1338

  • 95% fully waterproof (pending garage door installation)
  • tiling underway
  • plasterboarding/ drylining 100% complete
  • internal painting ongoing
  • internal joinery and fitout carpentry at 40%
  • kitchens 50% installed

Lots 1339 to 1345

  • 95% fully waterproof (pending garage door installation)
  • scaffold has been recently dropped
  • plasterboarding/ drylining completed
  • internal painting has commenced
  • internal joinery and fitout carpentry at 20%
  • kitchens 20% installed

Lots 1004 to 1009

  • 90% fully waterproof (pending garage door and sunhoods installation)
  • cladding completed and external painting underway
  • mechanical and electrical rough in completed
  • plasterboarding/ drylining 40% complete

Lots 1227 to 1232

  • 80% fully waterproof
  • cladding completed and external painting underway
  • mechanical and electrical rough in completed
  • plasterboarding/ drylining 30% complete