Welcome to another construction update for Newport Townhomes. We are very excited about the progress of our new Townhomes and want to share the latest details with you!

Check out the drone video to see our latest progress >> WATCH VIDEO

 

LAKEVIEW RELEASE
Our Newport Townhomes opposite Spinnaker Park and Newport Lake are progressing well and due for a June 2020 completion.

- Project is fully roofed allowing us to get things done even when it rains
- Windows and cladding are approaching completion and scaffolding has come down, revealing the stunning architect designed facades
- All External window and Doors have been installed (except for garage door which will come later)
- External painting is completed (balcony areas are currently being worked on)
- Internal joinery fitout has commenced
- Tiling will start in March month

 

CENTRAL RELEASE
The Newport Townhomes Central Release is slightly behind the Lakeview Release due to weather and is tracking for a July/August 2020 completion.

Lot 1332 to 1338
- Structural framing is completed 
- Roofing and cladding work is nearing completion 
- External painting has commenced but is being delayed by weather 
- External doors and window installation is nearing completion 
- Internal dry lining and waterproofing has commenced
  

Lot 1339 to 1345
- Structural framing is completed 
- Roofing and windows are being installed 
- Cladding work is works ongoing 

  

Lot 1004 to 1009 & Lot 1227 to 1232 
- Structural framing is nearing completion  
- Roofing is currently being installed 
- Cladding install has commenced
 

 

}