06 September 2018   

5min read
This month with stage one completed we were excited to welcome residents as they settle into their new homes. Watch the drone footage below to see the progress over the entire site.

Stage 1 - complete and settled
Stage 2 - Internal fit outs, kitchen and painting, pool tiling complete and landscaping commenced
Stage 3 - External cladding and painting, internal plasterboard commenced and first kitchens have been installed
Stage 4 - Slabs are being poured and first frames have commenced