Click below to see the construction progress made in February at Vida. Stage 1 homes at the entry to the site are progressing very well!

Stage 1 - roofs, skylights and solar are complete. Windows have been installed and cladding and plasterboard is underway.

Stages 2 – frames are well underway, reaching first floor and truss level across the stage; roofs are starting to go on the Isabelle’s this week!

Communal areas – internal road now fully cut and the driveway has been poured. The foundations for the swimming pool have been poured and retaining walls are under construction.